The Magazine that never took off

I work in the marketing team of a newspaper, last year the chief editor came up with an idea to launch a new magazine which will be handling the formula one news along with drag racing and other motor racing news. Since we didn’t have any project management team in our newspaper; we were given the responsibility to manage this project.

None of our team had any idea on how to manage a project, so we wrote down some tasks and we wrote the plan and assigned responsibilities. Our plan was exactly as follows:

1-      get the written content  (journalism department)

2-      get the advertisements and produce the magazine (marketing Department)

3-      Print the magazine (the magazine was going to be printed in house).

The first Issue of the Magazine
The first Issue of the Magazine

we faced a lot of problems while implementing the project but our worst problem is that the Magazine size was supposed to be 28cm x 28cm but it was changed to 20cm x 20cm in the last minute because it wouldn’t fit in the newspaper box to be distributed along with the newspaper so we had to reduce the size of our magazine design in the last three days before the issue. We managed to do it but the magazine came out with a lot of mistakes like some of the pictures came out to be a low resolution pictures due to the last minute size change, advertisements had the writing on them too small. This caused a bad reputation about the magazine. The magazine was published twice and it was shut down due to low readership and bad reputation. This made me think of how could we have made it better as a project and avoided this failure?

10JBZuk
Plan! Plan! Plan!

After taking the MGT 598 Class I realized the answer to my question, which was: Plan your project or get Planned by it! We should have had the tasks broken to a more detailed tasks and form a work breakdown structure while assigning responsibly to each task.  By determining our deliverables then dividing them to smaller deliverables and assigning responsibilities to them, and scheduling them on a gantt chart , while communicating the plan to the employees.

We also should have done a risk management plan and have a contingency plan ready to be initiated once we face any obstacles. By brainstorming and listing the possible risks then going through them identifying the implications of each of them and then rank them based on which is most probably going to happen, then we should have had a contingency plan by choosing weather if we want to mitigate, transfer, avoid or accept this risk.

0601.SUMMARY_ProjectPro_300x166.jpg-550x0
Microsoft Project 2013

I am now training my teammates to use Microsoft project in their free time, so whenever we do a project like the racing magazine or a supplement, we can use Microsoft projects to better organize our project. I been hearing rumors at our organization, that there will be a new magazine project which will be about tourism in Bahrain and outside Bahrain. Do you think that the tourism magazine will be successful?